Hi,

I am using version 6.5.54 and I wanted to know how to schedule the same Job to run Monday-Saturday at 4:00am and Sundays at 10:00am?

Anton Roberts

Official comment

Avatar

Hello Anton, 

In version 6, you will have to put the job inside a setup and schedule the setup for the second schedule. For example, Job A can be scheduled to run Mon-Sat at 4am, and then put Job A into a Setup, then schedule the setup for Sunday at 10am.

In version 7, we allow for multiple schedule trigger elements on a single job, which negates the need to put the job inside of another to schedule it.